Eaton Terrace Remodel
Lakewood, CO, USA
Eaton Senior Communities
47,000 Sq. Ft., 64 Units
Senior Living, Affordable Housing, Multi-Family Housing, Independent Living
The Summit Assisted Living conversion project is a major renovation of a vacant six-story tower that is a part of the larger Eaton Community campus in Lakewood. Work includes structural and MEP retrofits and extensive unit renovations that include plumbing stack additions and rerouting, electrical redistribution, demising wall relocations, and unit buildouts.
Pinkard "rescued" this project for Eaton Senior Communities when the originally hired contractor was replaced during the preconstruction phase. When Pinkard entered the project in May 2018, midway through the schematic design phase, the project was almost $6 million over budget and falling dramatically behind the owner's tight schedule. Because the tower was in the process of being vacated, the delay significantly imperiled the owner's revenue projections for 2018/ 2019 and created a dramatic need for urgency and efficiency within the Pinkard preconstruction team.
The owner's program challenged the Pinkard preconstruction team to find the most economical ways to consolidate 74 smaller assisted living (AL) units into 64 larger independent living (IL) units. The consolidation process included finding the best utilization of existing plumbing stacks
Following several timely partnering and design charrettes, the OAC team agreed upon a value engineering plan that enabled Eaton to maintain nearly all of its original program while meeting the owner's $6.4 million budget.
Pinkard's unit massing/revenue studies with Eaton and EJ Architecture were key to budgetary success in preconstruction. During budgeting/VE, Pinkard constructed an architectural mockup of a proposed unit to enable the ownership team to visualize proposed unit sizes better. To accelerate the design phase and allow construction to commence closer to Eaton's originally projected start date, the team agreed to combine the design development drawing phase with the construction document phase. This approach shaved roughly six weeks off the design schedule.
Despite the considerable delays associated with the changeover to Pinkard during preconstruction, Pinkard was able to complete the project within budget and only 13 days beyond the completion date set by the original contractor.
Construction on this affordable housing project was privately funded.