Creative Conceptual Programming and Budgeting
On 4725 South Lowell, The original project plan conceived by Denver Housing Authority (DHA) and architect WORKSHOP8 involved renovating...
Strong Pricing and Budget Phase Leadership
CSU hired Pinkard to work with the architect during programming to assist with pricing and budget, instead of at the end of schematic...
Pinkard Self Performs Unique Design Features
On the Moorhead Recreation Center project, BRS’s amazing rope wall was thoroughly mocked-up in miniature during design. During bidding,...
An Immense Natatorium Sequencing Challenge
Pinkard Construction Company won the Moorhead Recreation Center project through a competitive bid process. Scope of work included...
Next-Level Site Logistics Planning
Eliminating Early Obstacles at VIDA “Too many site logistics plans get ignored by the trades because they don’t change with evolving...
Critical Roofing Crisis Averted
Two weeks before roofing on Vida was scheduled to begin, we got the devastating news that our roofing subcontractor was closing its Denver...
First-of-Its-Kind Approach to Dry-In
With “normal” mid-rise construction, a building has to be completely dried-in before electrical rough-ins can begin. This means that the...
Avoiding $1 Million in Change Orders
While working on VIDA Senior Housing, groundwater rose into every hole we dug, due to the sub-standard soils, and would not flow...
Frasier: a $100M Success Story
Whether a Pinkard project is $1 M or $100 M one thing stays the same: Client service. When the Frasier master plan expansion was...